Flamanville-1, France

Overview
CURRENT STATUS
Operable
DETAILS
Reactor TypeCommercial Reactor
ProcessPWR
VendorFramatome
OwnerElectricite De France
ModelP4 REP 1300
OperatorElectricite De France
Capacity Net1330 MWe
Capacity Gross1382 MWe
Capacity Thermal3817 MWt
 
CONSTRUCTION AND OPERATION
Start Construction1 December 1979
Criticality29 September 1985
Grid Connection4 December 1985
Commercial Operation1 December 1986
 
OPERATING PERFORMANCE
Output Life212.23 TWh
Capacity Factor Life68.6 %
 
Flamanville 1 and 2

Flamanville 1 and 2


 
 


Reactor Operational Details

YearReference Unit Power MWAnnual Output GWhAnnual Time On Line HoursCapacity Factor %Operational Factor %
1985129021.0848000
1986129052734840100.697.6
198712907150.8565663.364.6
198813307175575761.465.5
198913308775.16714675.381.6
199013307089.98636060.872.6
199113305882.88548150.562.6
199213307606.83590165.167.2
199313309301.82793679.890.6
199413307145.81651561.374.4
199513307665.06665465.876
199613308598.28705073.680.3
199713306853.94552958.863.1
199813309469.38785581.389.7
199913306979.37590659.967.4
200013308035.27660768.875.2
2001133010038.55812686.292.8
200213308141.77673669.976.9
200313307510.77609064.569.5
2004133010630.0586689198.7
200513309099.89762778.187.1
200613307790.93667566.976.2
200713309595.59804182.491.8
200813304962.39401842.545.7
200913306956.71559359.763.8
201013308519.72695573.179.4
201113309572.66776882.288.7
201213306778.1256185864
201300000
Total:212620.81

Source: Operating details - IAEA PRIS
Note: "0" signifies a zero value, or no data available. Data from 1972 or later. 

Quick Search