Table
1: Schedule for commissioning and commercial operation at Temelin NPP.
|
||
|
|
||
|
Activity |
Unit 1 |
Unit 2 |
|
|
||
|
Containment integrity testing* (leakage test and strength test) |
Done |
Planned |
|
Control room technology testing |
Done |
Planned |
|
Primary circuit integrated hydro-testing |
Done |
Planned |
|
Fuel loading into the reactor (start of physical commissioning) |
Done |
Planned |
|
Start of commercial operation after complex testing and successful 144 hour test |
Planned |
Planned |
|
|
||
|
*Strength
and leakproof testing of Temelin unit 1 containment took place during
the period from 14 December 1998 through 5 January 1999. The containment
met all strength and leakproof criteria. The leak amount found during
the leakproof testing is one order lower than the prescribed values. The
test results achieved can be compared to the best results achieved abroad.
|
||
|
|
||