Table 1: Schedule for commissioning and commercial operation at Temelin NPP.

Activity

Unit 1

Unit 2


Containment integrity testing* (leakage test and strength test)

Done
01/1999

Planned
12/2000

Control room technology testing

Done
06/1999

Planned
01/2001

Primary circuit integrated hydro-testing

Done
03/2000

Planned
07/2001

Fuel loading into the reactor (start of physical commissioning)

Done
07/2000

Planned
11/2001

Start of commercial operation after complex testing and successful 144 hour test

Planned
05/2001

Planned
08/2002


*Strength and leakproof testing of Temelin unit 1 containment took place during the period from 14 December 1998 through 5 January 1999. The containment met all strength and leakproof criteria. The leak amount found during the leakproof testing is one order lower than the prescribed values. The test results achieved can be compared to the best results achieved abroad.