Table 1: Performance and cost data for new baseload power plants in Finland.

 

Nuclear power plant

Coal-fired condensing power plant

Combined cycle gas turbine plant

Peat-fired condensing power plant


Electric power (MWe)

1250

500

400

150

Net efficiency rate (%)

35

41

55

38

Investment costa (million euros)

2186

407

229

145

Investment cost per power output capacitya (euros/kWe)

1749

814

572

964

Fuel prices (euros/MWhf)

1.00

4.20

10.93

5.89

Fuel costs of electricity production (euros/MWhe)

2.86

10.26

19.88

15.49

Annual fixed operation and maintenance costs (percentage of investment)

1.5

2.0

1.5

2.5

Variable operation and maintenance costs (euros/MWhe)

3.41

4.92

0.31

3.10

Economic lifetime (years)

40

25

25

20

Interest rate (%)

5.0

5.0

5.0

5.0

Annuity factor (%)

5.828

7.095

7.095

8.024


a The interest during construction is included in the investment cost. For the nuclear power plant, the initial fuel loading is included in the investment.