Table
2: Electricity generation costs of the four baseload alternatives as
a function of annual full-load operating hours.
|
||||
|
|
||||
|
Operating
hours |
Electricity generation cost (euros/MWh) |
|||
|
Nuclear power plant |
Coal-fired condensing power plant |
Combined cycle gas turbine plant |
Peat-fired condensing power plant |
|
|
5000 |
31.94 |
29.99 |
30.01 |
38.89 |
|
6000 |
27.66 |
27.52 |
28.37 |
35.50 |
|
7000 |
24.60 |
25.75 |
27.20 |
33.09 |
|
8000 |
22.31 |
24.43 |
26.33 |
31.27 |
|
8400 |
21.55 |
23.99 |
26.03 |
30.67 |
|
|
||||
© copyright The Uranium Institute 2000