Table 2: Electricity generation costs of the four baseload alternatives as a function of annual full-load operating hours.

Operating hours
(hours/year)

Electricity generation cost (euros/MWh)

Nuclear power plant

Coal-fired condensing power plant

Combined cycle gas turbine plant

Peat-fired condensing power plant

         

5000

31.94

29.99

30.01

38.89

6000

27.66

27.52

28.37

35.50

7000

24.60

25.75

27.20

33.09

8000

22.31

24.43

26.33

31.27

8400

21.55

23.99

26.03

30.67


Nuclear Power: Least-Cost Option for Baseload Electricity in Finland