Details

Reactor Type Gas-Cooled Reactor (or GCR)
Model MAGNOX
Owner Nuclear Decommissioning Authority
Operator Sellafield Limited

Timeline

Construction Start Saturday, 1 August 1953
First Criticality Tuesday, 1 May 1956
First Grid Connection Monday, 27 August 1956
Commercial Operation Monday, 1 October 1956
Permanent Shutdown Monday, 31 March 2003

Specifications

Capacity Net 49 MWe
Capacity Gross 60 MWe
Thermal Capacity 268 MWt
Design Net Capacity 35 MWe

Operational History

Electricity Supplied (GWh)

Energy Availability Factor (%)

Total Electricity Supplied (GWh)

Reactor History

Year Reference Unit Power (MWe) Annual Time Online (Hours) Electricity Supplied (GWh) Operation Factor (%) Energy Availability Annual (%) Energy Availability Cumulative (%) Load Factor Annual (%) Load Factor Cumulative (%)

Source: Operating details - IAEA PRIS


See Also

Nuclear Power in United Kingdom

Related News

WNN articles on United Kingdom
Subscribe to receive updates on news