Also known as Zaporozhye-2, Zaporizhzhya-2
Details
| Reactor Type | Pressurized Water Reactor (or PWR) |
|---|---|
| Model | VVER V-320 |
| Owner | |
| Operator |
Timeline
| Construction Start | Thursday, 1 January 1981 |
|---|---|
| First Criticality | Friday, 28 June 1985 |
| First Grid Connection | Monday, 22 July 1985 |
| Commercial Operation | Saturday, 15 February 1986 |
Specifications
| Capacity Net | 0 MWe |
|---|---|
| Capacity Gross | 1000 MWe |
| Thermal Capacity | 0 MWt |
| Design Net Capacity | 0 MWe |
Operational History
Electricity Supplied (GWh)
Energy Availability Factor (%)
Total Electricity Supplied (GWh)
Reactor History
| Year | Reference Unit Power (MWe) | Annual Time Online (Hours) | Electricity Supplied (GWh) | Operation Factor (%) | Energy Availability Annual (%) | Energy Availability Cumulative (%) | Load Factor Annual (%) | Load Factor Cumulative (%) |
|---|